Site survey S-0001
J-0005 · Grace Community Church · Steeple flashing and metal roof repair
By Chris Bell, Nov 20, 2026 10:30 AM
Nothing in this survey needs attention.
Ground and setup
| Ground | Compacted gravel / base, 4,000 psf Gravel yard inside the fence, compacted base. |
| Slope | 0.5% |
| Heaviest crew | 52,000 lbs |
| Crew mats | 4 × 4 x 16 ft 812 psf under a mat |
| Location | 36.36400, -87.00900 |
Hazards
| Power lines | 35 ft from the crew, 69 kV Minimum clearance 15 ft (OSHA 1926.1408). 69 kV line along the north fence. Co-op lineman on site; spotter on the north side. |
| Underground | Yes: Ground grid and conduit runs inside the fence. Locate ticket TN-SAMPLE-0001, good through Dec 7, 2026 |
| Access | OK: Gate code from Paula. Turn in from the east side. |
| Swing obstructions | None noted |
| Traffic control | Not needed |
Notes
Transformer comes in on a lowboy; set it from the south pad.
Photos